RENEWING OF THE NETWORKS ARE CONTINUED

Image

 

Carried out purposeful measures at the state energy system, construction work with the applying of new technology makes opportunity for supplying of the consumers with quality and regular electric power. Intended technical measures are continued in the line of increasing of the level of technical – economical indicators, by the way, supplying of stabile transmission of electric power.

According to the information given by “Aghsu Electric Network” to the Press – release of “Azerenergy” JSC, 2 traverses were constructed, 24 stands and more than 3 km line  were repaired during implemented different type repair work at Gurjuvan, Ilkhichi, Lengebiz TL by 10 kV and at other lines. At the same time, about 1,5 km line was changed, 3,4 km was repaired during operated repair work at the lines by 0,4 kV.

Lets`  noted that, different setting repair work was operated at the transformer points belonging to the enterprise. In general, repair work was operated at 6 TP, 9 transformers were repaired and put into operation.

By the way, repair work were also carried out at the transformer by 5,6 MVA of Broyler s/s by 110 kV, the transformer by 10 and 2,5 MVA of YSHK s/s by 5,6 MVA and the transformer by 16 MVA of Aghsu s/s.

One of the measures for decreasing of losses is construction of meter in the special boxes, without obstacles places. Relevant measures in the line of it was continued during last three  months of the current year – noted source, is also give information about violations of rule of electric power of 12 consumers (11 of them belongs to consumers group). Discovered infringements were relevantly acted and more than 28 00 manat use value of more than 474 00 kWh (about 449 00 kWh belongs to private consumer group) loosed electric power was restored. Some part of this sum was repaid during financial period.

Lets` noted that, violations of rule of electric power of 119 consumers (95 of them belongs to private consumer group) at the enterprise service territory during 7 months of the current year. And more than 226 00 manat use value of more than 3768 00 kWh (more than 2975 00 kWh belongs to private consumer group) loosed electric power was restored. Some part of this sum was repaid as a result of carried out relevant measures and these type of measures are implemented in the line of repaying of the remainder sum.