PRELIMINARY MEASURES SHOW ITS RESULTS
Carrying out of capital and maintenance repair work at different powered distribution and transmission equipments in order to supply of the consumers with quality and stabile electric power, decrease of losses are the main orders standing in front of us. Unpleasant situations were happen in available climate condition as a result of carried out purposeful measures in the line of preparation of the network to season. Quality and quantity changes were achieved in electric support of the consumers.
It was noted in the information given by “Khachmaz Electric Network” to the Press – release of “Azerenergy” JSC.
As the source informed, more than 3,6 km line was substituted with new one and 62,3 km distance was maintenance repaired during carried out some repair work at “Yerguc”, “Nizova” TL by 10kV and at other ones feeding by “Khachmaz” s/s during last three months of the current year. At the same time, cutting work was implemented at 32,2 km distance, 7 ones were substituted with iron ones and the same numbered were made. Beside all of them, 17 transformer points were repaired and different powered 4 transformers were also repaired and put into operation.
Lets` noted that, three transformers were substituted with new ones in order to decrease of technological looses.
By the way, about 240 meters were constructed, more than 2,3 km cable was installed during carried out reconstruction and repair – restoration work in accordance to construction of meter – account complete in the special boxes and in without obstacle places.
Violations of rule of electric power of 6 consumers were discovered during carried out spot – checks at the enterprise service territory in June of the current year. Discovered infringements were relevantly acted and use value of more than 29 00 kWh (12 00 kWh belongs to private consumer group) loosed electric power was restored.
Lets` noted that, 18 statements were drawn up during 6 months of the current year and about 30 thousand use value of more than 4992 00 kWh (about 3863 00 kWh belongs to private consumer group) loosed electric power was restored. Some part of this sum was repaid as a result of carried out relevant measures and relevant measures are operating in the line of repaying of the remainder sum.