PREPARATION TO AUTUMN – WINTER IS CONTINUED

Image

"The current facilities and equipment, high-voltage line in the regular inspections, to take preventive measures for troubleshooting, as well as the implementation of planned measures in preparation for the autumn-winter season, our main task. To do this, we need to mobilize the collective strength." "Mingachevir REN" the press service of "Azerenergy" JSC the report says.

According to the source, in August, a significant number of service areas, and major repairs were carried out. Two 20-35 kV, one of 6-10 kV oil circuit breakers were repaired. The equipment has been repaired the same as the current three to five. Nevertheless, the current vacuum switches 6-10 kV repaired equipment 8.

Repair includes two power transformers of 110 kV, 220 kV one 110 kV circuit breakers includes six parts. Three units of 220 kV oil circuit for the team mechanics in the maintenance was put into operation.

In August, "Mingechevir high-voltage transmission", 110-kilovolt line service personnel 1st "Ganja" TL 124 and 133 of the insulator post 18 have been replaced by new ones. 1st 110 kV, including overhead line "City" was renovated. These interim strut 33, 18.32 and 44 insulators PSD-70 changes the brand, number 6 is anchored to the previous state were broken  shunt.

The main power line of 110 kV network of the 3rd "Home" TL 53, 55, 66 and 107 of the intermediate crude 40 70 E-insulator PSD equipment  substituted with new ones.

"Mingachevir REN" and overhaul of the company's staff work.