TECHNICAL OPPORTUNITIES OF THE NETWORKS WERE MUCH MORE IMPROVED

Image

Any problem was not observed in electric power supply of “Imishli Regional Electric Network” (REN) in spite of  non regular climate condition observed  at the republic territory in November of last year and in February of this year. These type achievement were achieved as a result of carried out reconstruction and repair – restoration work in accordance to preparation to autumn – winter during last year.

According to the information given by mentioned regional enterprise to the Press – release of “Azerenergy” JSC, reconstruction and repair – construction work were implemented at TL by 35 kV and more during last three months. By the way, construction work of auto transformer number 2 by 240 MVA at Imishli s/s  by 330 kV is going to be end. At the same time, the auto transformer number 1 by 16 MVA was substituted with one by 25 MVA.

Lets` noted that, extreme loaded transformer by 16 MVA was substituted with one by  25 MVA at “Yeni Beylagan” s/s by 110 kV. In accordance to perspective improvement connection of the second transformer to this s/s is intended.

It should be noted that, reconstruction work was also implemented at “Kurdamir”, “Aghjabadi” and “Sabirabad” s/s by 110 kV. So that, oil circuit breakers were substituted with modern type ones at “Aghjabadi” s/s and at present, substituting of oil circuit breakers with modern type, reconstruction of cable canals, changing of security  - management cables are implemented at mentioned two of s/s.

Lets` noted that, analogical repair work were implemented at “Saatli” s/s by 35 kV. At the same time, the transformer by 2,5 MVA were capitally repaired at “Vidadi” s/s number 1 and 2 by 35 kV.

As the source informed, different setting repair work were implemented at the III “Shirvan”, the I, II and III “Kurdamir”, the I “Sabirabad” TL in order to increase regularity. Analogical measures were realized at “Mollakend”, “Kebirli budaglanmasi”, “Khalaj”, “Jarli”, “Kovlar”, “Ulajali”, the III “Aghjabedi” TL by 35 kV.

By the way, fire safety is also in the center of the attention. So that, place for swimming pool was grounded, construction of accident oil storehouse was finished at “Aghjabadi” s/s by 110/35/10 kV. In general, the territory  of the sections by 330-110-35 kV was cleaned of mass. Fire extinguisher means were substituted with new ones at sections by 330 – 110 kV.

It should be noted at the end that, carried out and at present continued work will make opportunity for improvement of stability of energy system.