“MINGACHEVIR REN”: STABILITY OF TL IS IN THE CENTER OF THE ATTENTION

Image

Carrying out of capital and maintenance repair work at s/s, distribution installations in order to supply  the consumers with quality and stabile electric power and decrease of the losses are the main orders standing in front of power engineering specialists. Relevant measures are implemented in the line of it at the service territory of “Mingachevir Regional Electric Network” as at other energy objects. Strategic important “Absheron” TL by 500 and 330 kV was also in the center of the attention during last three months. Different setting measures were implemented at these TL.

It was noted in the information give by mentioned enterprise to the Press – release of “Azerenergy” JSC.

As the source informed, analogical measures were continued at TL by 35, 110, 220 kV. So that, the stands were repaired, damaged insulators were substituted with new ones and paint work was carried out  at relevant parts. In general, more than 35 km part of the same tensioned TL belonging to the balance was also repaired.

Repair work was operated at “Barda – Tartar”, “Mammadli”, “Naftalan”, “Ganja”, “Aghsu”, “Mingachevir” and at “Gabala” TL.

Lets` noted that, different setting repair work was implemented at “Gabala” s/s by 220 kV, “Barda”, “Ujar” and “Kurekchay” s/s by 110 kV, by the way, 24 oil circuit breakers were capital repaired.

Under the information given by the source, the transformer by 110/35/10 kV was substituted with the transformer by 110/35/6 kV in order to much more increase the stability of electric power supply. At the same time, the transformer by 16 MVA was substituted with the transformer by 25 MVA at “Chemenli” s/s by 110 kV. Beside all of them, 7 set oil circuit breakers were substituted with modern type breakers at the same tensioned “Sheher” s/s.