POWER OF “SIYAZAN” S/S IS INCREASING

Image

“Khachmaz Regional Electric Network” (REN) and electric networks belonging to its structure take the main part in electric supply of northern regions of the republic. The collective are assiduously try to execute the measures plan in necessary level.

According to the information given by REN to the Press – release of “Azerenergy” JSC, the transformer number 1 by 25 MVA and number 2 by 16 MVA were repaired, current transformer by 110 kV and voltage transformer at the I and II the same tensioned  system tire-cover were substituted with new one at “Khachmaz” s/s by 110 kV. At the same time, oil circuit breaker at some lines by 10 kV were substituted with vacuum breaker.

Lets` noted that, analogical measures are also implemented at “Siyazan” s/s. At present, substituting of the transformer number 2 by 20 MVA with the transformer by 31,5 MVA are carrying out.

As the source inform, different powered transformers were repaired and put into normal work regime at “Khudat”, “Shabran”, “Guba”, the III “Beynelmilel” and at other s/s.

It should be noted that, 60  insulators at TL by 330 kV, more than 580 insulators at TL by 110 kV, about 100 insulators at TL by 35 kV were substituted with new ones. At the same time, 2 traverses and the same numbered porch were changed at “Khudat – Yalama” TL by 110 kV, 2 wooden anchors were substituted with metal ones at “Guba – Gusar” TL by 35 kV, 3 anchors and 2 wooden mid stands were substituted with metal anchor stands at “Ajakhur” TL.

By the way, the accidents are prevented at the 227 – 234 stands of “Khachmaz” TL by 330 kV. There was no observed any serious defects at the line during last period. But anomaly  climate condition observed during last period makes necessity for preventing of some indispositions.  As a result of carried out measures the number of natural calamity was decreased to minimum.

Lets` also noted at the end that, fire safety is also in center of the attention there. So that, fire extinguisher posts were supplied with relevant accessories at the s/s, 50 cubic meter accident oil capacious and water reservoir  were constructed, additional water lines were installed and cable canals were reconstructed. At the same time the territory was cleaned of dry grass.