RECONSTRUCTION WORK IS CONTINUED

Image

Carrying out of capital and maintenance repair work at the s/s and transmission equipments, decreasing of losses to minimum  in order to supply the consumers with quality and regular electric power are the main orders  standing in front of power engineering specialist. Corresponding measures are implemented in the line of it, at Mingachevir Regional Electric Networks (REN) as at other energy objects. According to the information given by REN to the Press – release of “Azerenergy” JSC, more than 40 km part of high voltaged TL by 35 kV and more were capital and maintenance repaired in order  to much more increase of the stability during last three months of the current year.

Lets` noted that, more than 20 transformers, more  than 70 oil circuit breakers, different numbered vacuum and  insulating gas circuit breakers were put into normal work regime at s/s by35 kV and more of the network.

Reconstruction work  was implemented at 94 km of TL by 0,4 kV, at more than 95 km of TL by 6-10 kV. At the same time, capital and maintenance repair work were implemented at the transformer points.

Beside it, reconstruction work was implemented at “Gabala” s/s by 110 kV.

The transformer by 16 MVA was substituted with new one by 25 MVA at “Chemenli” s/s by 110 kV and reconstruction work was carried out  at the same tensioned  “Hajili” s/s.

Lets` noted that, construction of “Aghdash” s/s by 220 kV and “Goranboy” s/s by 330 kV are continued in order to strengthened stability of the state energy system.

Under the information given by the network, reconstruction work is continued at the lines by 0,4 – 6 – 10 kV of “Barda”, “Naftalan”, “Yevlakh”, “Mingachevir” and “Goranboy” electric networks. Construction of more than 2500 meters, about 3 km SIL type cable and different numbered iron - concrete stands are belonging to these type of measures.

Lets` remind that, about 1700 km high voltaged TL and 49 s/s are belonging to the enterprise balance.