ENERGY SYSTEM OF THE REGION IS RENEWED

Image

Relevant measures are carried out at Ganja Regional Electric Network (REN) which plays important role in meeting requirements of western regions in order to improve technical indicators, supply the consumers with much more quality and regular electric power, by the way, preparation to autumn – winter season. It was noted in the information given by the network to the Press – release of “Azerenergy” JSC about implemented capital and maintenance repair work at  TL and TP (TP) located at administrative territory of Goygol, Shamkir and Gazakh.

As  the source informed, more than 1130 stands were grounded, about 56,2 km coaxial cable and about 71,3 km SIL type cable by 0,4 kV were installed. Beside it, 3 TP and 5 CTP are constructed at “Goygol Electric Network”.

Lets` noted that, about 3,8 km part of “Goygol”, “Nadel”, “Kokeltme” by 10 and 6 kV  and other TL and 4,2 km part of the lines by 0,4 kV were capital repaired. At the same time, about 132 transformers by 52,2 MVA were capital and maintenance repaired.

Under the information given by “Shamkir” EN, important measures were implemented in order to improve electric power supply and develop the activity of the region electric system. That is why, carried out work in the line of substituting of the posts with new ones is also important. So that, more than 1300 stands were constructed there, more  than 32,2 km coaxial cable and more than 43,2 km SIL type cable by 0,4 kV  were installed. Two TP and 5 CTP were   constructed.

Lets` also noted that, 24,7 km of “Chingil”, “V.  Khuluflu”, “Posanli”  by 10 kV and other lines were repaired. At the same time, reconstruction and repair work were also operated at the network by 0,4 kV. So that, about 22,3 km of mentioned network was repaired and about 12 km new line was installed. Different setting repair work were carried out at 207 TP and at more than 200 transformers total power more  than 84,3 MVA.

In order to strengthened the regularity of the power plant at “Gazakh” EN about 8,6 km the I and II “Shikhli”, “Dash Salahli”, “Huseyinbeyli”, “Gazakhbeyli”  by 10 and 6 kV and other TL were repaired. More than 12 km of the lines by 0,4 kV were also repaired.

By the way, 7 TP belonging the enterprise balance  were capital repaired. At the same time, 79 transformers by 22 MVA were repaired.

It  should be noted that, carried out necessary work at the region electric power supply sphere increased the quality and exploitation level.