RECONSTRUCTION WORK IS CONTINUED AT IMISHLI S/S

Image

 

Preparation work to autumn – winter season is mainly over at all s/s, transformer points, by the way, complete transformer points belonging to Imishli Regional Electric Network” as at all energy objects. Some measures were implemented in the line of carrying out of some capital repair work and technical inspection work, increasing of exploitation level of energy transmission and distribution system. By the way, the transformer number 2 by 240 MVA was put into operation at “Imishli” s/s by 330 kV. At present, substituting with new one of the transformer number 1 was begun.

According to the information given by mentioned enterprise to the Press – release of “Azerenergy” JSC, the transformer by 25 MVA was construction at “Sarijilar” s/s by 110 kV, the same tensioned oil circuit breakers and oil circuit breakers by 35 kV were repaired. At present, collecting of security electric circuits are operated there and after finishing this work the transformer will be put into operation.

Lets` noted that, the transformer number 2 by 40 MVA was repaired at “Aghjabadi” s/s by 110 kV. At the same time, oil circuit breakers were substituted with modern type at the input by 10 kV of the transformer number 1 and 2. Analogical work were also implemented at the part by 35 kV. At present, enlarging and reconstruction work were carried out at the parts by 110 and 35 kV.

Under other information given by the source, finishing of construction work of accumulator room meeting of modern requirements in the line of enlarging of “Boyuk Harami” s/s by 110 kV and capital repair work of the transformer by 3,2 MVA at “Akhtachi” s/s by 35 kV can be noted.

By the way, repair work were carried out at 264 transformer points belonging to electric network balance during three months of the current year.

Some measures were carried out in order to increase regular work of energy transmission system noted source is also added that, the insulators were substituted with new ones at the III “Shirvan” TL by 330 kV, color extinguishers were repaired at three stands. At the same time, the territory of the stands were cleaned of green mass. Analogical work were carried out at the III “Imishli”, “Parsabad”, the “I Sabirabad” and the “I Kurdamir” TL.

It should be noted that, two stands were substituted with new ones at “Garalar” TL by 35 kV coming out of “Imishli” s/s by 330 kV. At the same time, two new stands were constructed between “Zardab” and “Elven” TL by 35 kV. Beside all of that, the stands were changed at TL by 10 kV, the cables were changed in order to prevent of the losses, the territory of the stands were cleaned of green mass and other purposeful measures were implemented.

Fire safety is also in the center of the attention as at other objects. Constantly previous measures are carried out. Construction of accident oil storehouse was over at “Aghjabadi” s/s by 110 kV, support wall was constructed between the transformers number 1 and 2. At the same time, the territory of s/s and security zones of TL were cleaned of dry grass, surrounding of oil capacious equipments was cleaned of oil cover, control and measure apparatus were inspected and discovered indispositions were eliminated.

As the source informed, carrying out of enumerate measures is the main factors at energy economy. Continuing of reconstruction wok at the network is one of the main tasks at today’s` diary.