THE EQUIPMENTS ARE SYSTEMATICALLY MAINTENANCE SERVICED
“Khachmaz electric network” plays the main role in supplying with electric energy of northern regions. At present every think is under control as the first activity period. According to the information given by energy objects to the press – release of “Azerenergy” JSC, electric power production was about 26,7 million kWh during September of the current year. And it is 379 000 kWh more than predicted.
Lets` noted that, about 244,1 million kWh electric power was produced against 239 million kWh during 9 months of the current year.
Lets` also noted that, the role of the power plant is increased in the line of energy exchange between Russian Federation and our republic. So that, the power plant not only meet internal requirement but also it is the real participant of energy exchange.
Beside renovation work, systematically maintenance service was implemented at the enterprise equipments. So that, at present, the next maintenance service was begun at engine generators number 4, 5, 6 and 7 in 1600 hours exploitation limit.
Repair restoration work was carried out at the equipments of s/s by 110 kV, on the floor of halls and at some water pipes under open air in the line of preparation to winter. Engine – aggregates are ready to winter regime.
Fire safety is also in the center of the attention. So that, fire extinguisher equipments were constructed at 11 different places.