ENGINEERING – TECHNICAL MEASURES ARE CARRIED OUT

Image

 

All carried out engineering – technical measures give its positive result in preventing of energy loss, specifying of the consumption, increasing of total payment. 
Under the information given by “Imishli electric network” (EN) to the Press – release of “Azerenergy” JSC, about 17 million kWh electric power was produced in January of the current year. This indicator was more than 21,8 million kWh during the corresponding period of last year. Total payment was about 55 %. As a result of it, the consumption was about 20 % decreased, absolute increase was 2,2 % in the payment. By the way, more than 4,4 million kWh electric power was used under private consumer group and it is 3,2 million kWh less in comparison with the corresponding period of last year. The payment during account period was more than 74 %, this indicator was about 44 % during the corresponding period of last year.
Under the information given by “Sabirabad” EN, about 19 million kWh electric power (this indicator was more than 22,2 million kWh during the corresponding period of last year) was used. Total payment was more than 49 % (this indicator was 38 % during the corresponding period of last year). As a result of it, the consumption was 3,3 million kWh decreased and the payment was absolutely 11 % increased. By the way, about 14,4 million kWh electric power was used under private consumer group. and it is about 3,8 million kWh less in comparison with the corresponding period of last year. The payment was more than 45 %. This indicator was about 36 % during the corresponding period of last year.
Under the information given by “Fuzuli” EN, about 15,3 million kWh electric power was used in January of the current year. And it is about 32 000 kWh less in comparison with the corresponding period of last year.
And the total payment was more than 56 %.