THE RESULTS OF FIRST QUARTER
Improving the efficiency of equipment, power transmission system, stable operation and increase the level of the first quarter of the current year as a result of targeted measures, including technical and economic indicators of energy production in March was high.
According to the information given by the source to the Press – release of "Azerenergy" JSC of the country's largest producer of electricity, "Azerbaijan" Thermal Power Plant in the first quarter of 2016, the staff, as well as power units and equipment in March, reliable, stable and efficient operation provided. Forecast of production was fully implemented in accordance with the dispatch schedule. Basic equipment failure, which could lead to damage and there was not a single case of failure and rejection.
The station in March was 477.3 million kilowatt-hours of electricity. 572,4 million in the first year of energy quarter 1 billion kilowatt-hours of electricity passed energy system.
"Azerenergy" JSC in accordance with the approved maintenance schedule, the station at the end of March to the middle of the third power has been restored. At present, the schedule of sending, after 15-16 million kilowatt-hours of electricity produced per day.
"Mingachevir HPP cascade" of employees in March was 53.1 million kilowatt-hours of energy. During the first quarter, while the volume of production amounted to about 115 million kilowatt-hours. Energy savings have been significant useless.
In addition to the power generation for the maintenance and repair of the plant is in full swing. "Mingachevir" is number 5 overhaul of hydro, three transformers, current transformer was repaired. 110 and 220 kV substations, compressor and one of the current repairs, flood waters were cleared in the transmission channel.
In connection with the reconstruction of the yard of 110 kV and 220 at the entrance to the new foundation was established.
"Varvara HPP" was done as well.
Plays an important role in energy supply in the western region of the country, "Shamkir" and "Yenikend station" at the Central Chief of workers followed the instructions properly.
"Shamkir" in March, 72 million kilowatt-hours in the first quarter amounted to 159 million kilowatt-hours of electricity. They spend energy in electricity savings achieved Shamkirli special.
"Yenikend HPP" to the success of workers employed there. They are 600 thousand kilowatt-hours in March, 63,8 million kilowatt-hours of electricity in the first quarter, while private consumption was economical.
Also note that both the power plant and the transmission of the year, spring-summer flood water being prepared for installation. HPP equipment, maintenance and checkups installation continued maintenance crews.