REPAIR MEASURES WERE IMPLEMENTED

Image

"Azerenergy" JSC Electric Transmission Office "Mingachevir Regional Electric Network" in Mingachevir, Yevlakh, Barda, Ujar and Agjabedi in June this year in line and equipment as well as increase the level of substations to improve the quality and diversity Click on the targeted measures included in the Joint series continues repair work in June migrant 110/35/6 kV enterprise "Sheher" 63 MVA transformer substation 35 kV number 2 oil keyless entry and air line 6, № 30 key oil repair kV, 110 kV transformer number 1 and gas-insulated 35 kV ignition key to access the fat from the current repair. 110/35/10 kV team "Home" Movement has performed similar work. Thus, 10 kV 3 "Village" and the   line 35 kV oil circulation air line was restored. Number 1 63 MVA substation, switch 2nd line "Ucar" 110 kV, 10 kV "Pump" key in the current repairs amount of oil from the air line.

Current repair work 110/35/10 kV "Barda" and "Ucar" was held at the substations. 63 MVA, 110 kV circuit breaker - (3 units), 35 kV oil circuit block and tires - (2) The service of this kind.

110/35/10 kV "Agjabedi" substation in June to clear the interrupt. These two high-voltage transformers, 110 kV gas-insulated switchgear and the entry of oil circuit breakers 35 kV "Agjabadi-2" circuit overhead line, transformers, vacuum circuit breakers 1 and number 2, 10 kV 1 "City" TL maintenance of basic oil and left.

220/10/10 kV "Gabala" two 63MVA transformer substation 1 and number 3 oil circuit breakers 220 kV transformer was repaired.

"Mingachevir REN", belonging to the balance sheet of the company, which is a significant amount of overhead lines was repaired during the month of June. 220 kW I "Mingachevir" TL 20, 1st 110 kV "City" TL more than 100 insulators were changed, and four anchors is more than 10 insulators were replaced. In this process, 110 kV II "City" 1.6-kilometer section of the airport, and more than 20 insulators were removed and replaced during overhaul.

110 kV III "Basic" TL 40, Goranboy II "Veyisli" TL 8 insulators changed.

The remaining half of the year began with a collective enthusiasm network.