SAFETY RULES ARE IMPLEMENTED
About 3,5 milliard kWh electric energy was produced since "Baku Power Plant" was put into operation till to present time (01.07.2013). This factor was more than 270 million kWh during the I quarter of the current year.
According to the information given by the enterprise to the press - release of "Azerenergy" JSC, measures plan to autumn - winter season is systematically carried out.
Necessary technical service units, chemical analyzes were carried out, washed radiator. This version of 110 kV transformers were replaced with new air generator unity filters, air compressors have been renovated. Fire waterline was verified, automation, relay protection and measuring devices have been considered, mended, pipeline filters changed, gas regulated blocks were tested.
The source said that in the last six months of the inspection staff of electrical power equipment workshop, maintenance work carried out in accordance with the schedule of units 110 kV substation equipment has been repaired.
s/s high-voltage power transformers, circuit breakers, works disconnects service. Nine of the generator has been repaired.
It should be noted that fire safety for 6 months have been prepared and are being implemented. Fire pumps and repaired the water led to the current situation of labor. The territory of the station, fire hoses and fire-fighting equipment was provided headers. Fire inspection. Foam fire extinguishers have been working condition. 110 kV substation fire messages and was provided.
The area around the fire station and the computer room, which is a source of oil, herbs are always cleaned. Safety in the workplace is constantly monitored.