RECONSTRUCTION WORK IS CONTINUED AT THE NETWORK
Important measures are going to be done at “Saatli Electric Network” in order to improve exploitation level. According to the information given by the network to the Press – release of “Azerenergy” JSC, 220 new stands were grounded, 10 kV line in 8 km was installed during last period.
Lets` noted that, necessary measures were implemented at s/s. Transformer by 20 MVA was capital repaired at “Darti” s/s 110/35/10. At present, construction of circuit breaker by 110 kV of the transformer 16 MVA is also continued.
As the source informed, reconstruction of the network at the region is continued and SIL type cable in 209 km length was installed and more than 6500 smart – card type meters were supplied. Approximately line in 57 km length was reconstructed, 8 new transformer points were constructed. At present, network was reconstructed at Azadakend territory which has 332 consumers.
By the way, capital repair wok of the transformer number 1 by 10 MVA at “Saatli” s/s by 35/10 kV was also intended.