MINGACHEVIR REN: REPAIR WORK IS CARRIED OUT

Image

Capital and maintenance repair work were implemented at the s/s, distribution installations of Mingachevir regional electric network” (REN), by the way in the of preventing of losses in order to supply of the consumers with quality and stabile electric energy. The I, II “Absheron”, the I, II and VI “Mingachevir” and “Gabala” electric energy lines are in the center of the attention. These stands are systematically inspected and discovered indispositions are prevented.

It was noted in the information given by the enterprise to the Press – release of “Azerenergy” JSC during last three months of the current year.

As the source informed, lines were repaired at the II “Absheron” TL by 500 kV, stands number 1 and 472 were controlled and the trace was cleaned of green mass. Analogical measures were implemented at the I “Absheron” TL by 330 kV. At the same time, one metal stand was constructed at “Janavarli” TL by 35 kV.

Lets` noted that, different setting repair work were implemented at the II Ganja, the I – II Yevlakh, the Ujar TL by 110 kV, the I – II Mingachevir, Gabala TL by 220 kV, the III – V and VI Mingachevir TL by 330 kV, the I Samukh TL by 500 kV. By the way, about 11 km of TL were capital and maintenance repaired.

As the source informed, one entry oil breaker was constructed at “Bighir” s/s by 35 kV. Vacuum type breaker was substituted with other one at the I “Kand” TL in accordance to reconstruction work. New vacuum breaker by 10 kV was constructed   there in order to create connection with “Goygol” – 1 hydro power plant during current year.

By the way, construction of  circuit breakers at “Barda” s/s by 110 kV was continued. Beside it, different setting repair work were operated at “Aghsu” s/s by 220 kV and at “Ujar”  s/s by 110 kV during  current year.

About 20 transformers and 30 different type oil circuit breakers were capital and maintenance repaired at the s/s by 35 kV.

Lets` noted at the end that, carried out and intended measures in the line of it are systematically continued.