SUMGAIT HVEN: RECONSTRUCTION MEASURES ARE CARRIED OUT

Image

Collective of Sumgait High Voltage Electric Network are assiduously  try supply the consumers with quality and stabile electric energy as at other engineering enterprises. It is very important to supply s/s and high voltage electric network in good mending. Carried out measures during last months are estimable.

It was noted in the information given by mentioned enterprise to the Press – release of “Azerenergy” JSC.

Maintenance repair work was implemented at “Senaye Govshaghi” s/s by 220 kV during last three months, at the same time, insulating gas breakers were constructed for “Yeni Zabrat” TL by 220 kV and the II  “Senaye Govshaghi” TL by 110 kV. At the same time, repair work was operated at “Yashma” s/s by 330 kV. Lets` noted that, “Yashma” s/s plays the main role in supplying of consumers with quality electric energy and transmission of energy.

Under the information given by the source, new distribution switch yard by 6 kV was constructed at the transformer by 40 MVA number 2 of 135 s/s by 110 kV. At the same time, different setting repair work were implemented at Sumgait – 3 s/s by 110 kV during mentioned period. By the way, the VII and VIII Sumgait TL were substituted with cable lines.

Beside it, repair work was also implemented at the transformers and their equipments of Sumgait – 2, Kimyachilar, Sitalchay, Ceyranbatan, Goredil, Shamakhi, Masazir s/s by 110 kV and at other s/s.