YEVLAKH EN: VIOLATIONS OF RULE ARE PREVENTED

Image

Lots of measures were implemented and continued in the line of preventing of violations of rule of electric energy at “Yevlakh electric network” (EN) as at all electric networks (EN).

According to the information given by mentioned enterprise to the Press – release of Azerenergy” JSC, violations of rule of electric energy of 36 consumers (34 of them belongs to private consumer group)  were discovered during carried out spot – checks in March of the current year. Discovered infringements were relevantly acted and more than 149 00 manat use value of more than 2487 00 kWh (about 1398 00 kWh belongs to private consumer group) loosed electric energy was restored.

Lets` noted that, 112 infringements (103 of them belongs to private consumer group) were observed during the I quarter of the current year and about 432 00 manat use value of about 7199 00 kWh (5325 00 kWh belongs to private consumer group) loosed electric energy was restored.  About 79 % of this sum was repaid during financial period and relevant measures are operated in the line of paying of remainder sum.

As the source informed, about 11,6 million kWh electric energy was used under the enterprise in March of the current year and it is about 92 thousand less from the consumption of the same period of last year. By the way, consumption under private consumer group was about 234 thousand decreased and was about 3,8 million kWh. As a result of it, absolute increase was more than 4 % in the payment of energy bill in comparison with relevant period of last year.

Lets` also noted that, about 34,4 million kWh electric energy was used during the I quarter of the current year. As a result of consumption was 71 thousand kWh increased, absolute increase at the payment was 2,7 % under private consumer group. By the way, consumption was about 822 thousand kWh decreased and was more than 12,5 million kWh under private consumer group. Payment was absolutely 10,4 %.

Repair – restoration were successfully implemented at transformer points and TL and presently are continued – noted source was also give information about carried out measures at last three months.

As the source noted, more then 1,3 km line was capital repaired at the lines by 10 and 0,4 kV during mentioned period and 9 stands were substituted with new ones and 9 traverses were constructed.  At the same time, about 745 meter cable was installed. Capital and maintenance repair work were implemented at 7 TP, one transformer was capital repaired and connected to the network.