Reconstruction, capital and maintenance repair work were implemented in accordance to confirmed plan graphic at transformer points and TL belonging to balance of “Zardab” EN as at other electric networks (EN). These measures are successfully continued at the first month of the current year as last year.

According to the information given by mentioned enterprise to the Press – release of “Azerenergy” JSC, different setting repair work were implemented at “Sovkhoz”, “Bichaqchi”, “Seyidler” TL by 10 kV, “Elvend”, “Aghamalilar”, “Challi” TL by 0,4 kV and at other same tensioned TL during last three months of last year. In general, 5,7 km distance of these lines were capital and maintenance repaired. St the same time, different powered 25 transformers belonging to the enterprise balance were repaired and put into normal work regime.

Under other information given by the source, violations of rule of electric power of 18 consumers (5 of them belongs to private consumers group) were discovered in December of 2012. And more than 3200 manat use value of more than 529 00 kWh (more than 43 00 kWh belongs to private consumers group) loosed electric power was restored. In general, 146 infringements were discovered (115 of them belongs to private consumers group) under the enterprise during last year and about 218 00 manat use value of more than 3629 00 kWh (about 1805 00 kWh belongs to private consumers group) loosed electric power was restored. More than 89 % of this sum was repaid and relevant measures are operated in the line of paying of the remainder sum.

Lets` also noted that at the end, more than 3,7 million kWh electric energy was used in December of  2012 at the enterprise service territory. By the way, more than 1,8 million kWh electric energy was used by private consumers group.

By the way, about 47,3 million kWh electric energy was used under the enterprise during last year. Payment was absolutely 3 % increased in comparison with the payment of the same period of 2011. By the way, consumption was  about 19,5 million kWh by private consumer group, payment was more than 6 %.