RECONSTRUCTION MEASURES ARE IMPLEMENTED
Large scaled measures plan was prepared and continued in the line of strengthening of stability at distribution electric network system and supplying of the consumers with quality electric power. And these measures play the main role in supporting of the consumers with electric energy. Repair – restoration measures are implemented in time as always at the enterprise and carried out purposeful measures give its positive results. Paying of used electric power value beside restoring measures are in the center of the attention.
According to the information given by “Dashkesen electric network” (EN) to the Press – release of “Azerenergy” JSC, 28,4 million kWh, by the way about 2,2 million kWh electric energy was used under the enterprise during 11 months of the current year. These indicators were about 9,4 million kWh and more than 1 million kWh under private consumer group. As the source informed, repair work was implemented at about 6,1 km distance of the lines by 6-10-0,4 kV, more than 5,6 km line was reconstructed at the lines belonging to the enterprise during last months of the current year. At the same time, about 1,2 km cable line was installed.
Lets` noted that, reconstruction work was also implemented at TP. So that, one CTP and one transformer by 1000 KVA were constructed during mentioned period. Beside all of them, 38 transformers about 13,2 MVA were repaired and put into operation.
By the way, spot – checks were operated in the line of discovering of illegal use of electric power. So that, violations of rule of electric power of 18 consumers were observed at the enterprise service territory in November of the current year. And more than 84 00 manat use value of about 1401 00 kWh loosed electric power was restored. Some part of this sum was repaid during financial period.
It should be noted that, 130 infringements were discovered ring 11 months of the current year and discovered violations of rule were relevantly acted. About 258 00 manat use value of 4297 00 kWh loosed electric power was restored. Some part of this sum was repaid as a result of carried out measures and relevant measures are operated in the line of paying of the remainder sum.