THE NETWORK IS READY TO WINTER
Relevant measures are continued in the line of supplying of the consumers with quality and stabile electric power during autumn – winter season. These type of measures were implemented at “Absheron Regional Electric Network” (REN) which plays the main role in supporting of Absheron and capital around territories with electric power. According to the information given by the enterprise to the Press – release of “Azerenergy” JSC, executed measures are servicing regularity of transmission network.
As the source informed, reconstruction work was implemented in accordance to reconstruction of auto transformer number 3 by 400 MVA at switch yard by 300 kV under “Absheron” s/s by 500 kV. And at the same time, reconstruction measures are operated at SY by 220 kV. Auto transformer number 3 was placed and at present construction of its equipments were continued at “Mushfiq” s/s by 220 kV in order to much more strengthened of stability of energy supply.
Circuit breakers, tension and current transformers were substituted with new ones in accordance to reconstruction of “Sengachal” s/s by 220 kV. Repair work was also implemented at the same tension “Khirdalan” s/s.
Purposeful measures are operated for increasing of power of “Binagadi” s/s with much more quality electric power. So that, the transformer number 3 and 4 by 40 MVA was substituted with the one by 63 MVA. Construction of SY at “Zabrat” s/s was over and construction of the equipments were started.
Lets` noted that, carried out repair work at Hovsan s/s by 220 kV, Ramana, Zigh, the VIII km by 110 kV and at other s/s are belonging to these type of measures. As a result of it, intended measures are relevantly operated in accordance to autumn –winter season.
In additional, repair work was implemented at Surakhani, 205 and Gala s/s in order to improve work condition of the workers.
It should be noted that, at present construction of Boyukshor and Zabrat s/s by 220 kV is continued at the enterprise service territory.
Supporting of stability and without interval supplying under the enterprise is in the center of the attention. For this purpose, construction of two circuit TL between Sangachal PP and Mushvig s/s by 220 kV, Shimal and Hovsan PP and Zabrat s/s by 220 kV are continued. Aghsu and Gabala TL by 220 kV were constructed.
By the way, fire safety is also in the center of the attention as at other enterprises. The territory was cleaned of dry grass and surround of oil capacious equipments were cleaned of dirty oil. At the same time, after inspection of discovered infringements they were prevented. At the same time s/s were supplied with fire extinguisher equipments.