Relevant repair work was implemented at TL and transformer points in order to increase of service quality for consumers of Jalilabad EN, decrease of losses, paying of value of used electric power. The collective of the enterprise are assiduously try to handle their work well.

According to the information given by mentioned enterprise to the Press – release of Azerenergy JSC, violations of rule of electric power of 53 consumers were discovered during carried out spot – checks at the enterprise service territory in September of the current year. Discovered infringements were relevantly acted and about 84 00 manat use value of more than 1392 00 kWh loosed electric power was restored. More than 37 % of this sum was repaid during financial period.

Lets` noted that,  410 violations of rule of electric power were discovered  and more than 864 00 manat use value of more than 1 million 4407 00 kWh loosed electric power was restored. More than 31 % of this sum was repaid as a result of carried out measures and relevant measures were operated in the line of repaying of the remainder sum.

Lets` noted stressing to the source, 14,4 km of the lines by 10 kV were reconstructed, more than 11,8 km was capital repaired at the enterprise service territory during last three months of the current year.

It should be noted that, 23 TP were reconstructed, 53 of them were differently repaired during mentioned period. At the same time, 8 transformers about 1,4 MVA were repaired and connected to the network.