SHIRVAN TPP: REPAIR WORK IS CARRIED OUT

Image

Damaged parts were substituted with new ones at energy blocks and at their subsidiary equipments, heating covers were cleaned during repair work in accordance to applied repair schedule at Shirvan Thermal Power Plant”. As a result of it, technical economical indicators were improved in comparison with present situation of equipments of energy block. At present, the power plant is operated under the dispatch graphic.

According to the information given by mentioned enterprise to the Press – release of “Azerenergy” JSC,  about 220,8 million kWh electric power was produced at the power plant in August of the current year.

Lets` noted that, more than 2 milliard 16,8 million kWh electric power was generated there during 8 months of the current year.

Other technical economical indicators of the power plant is satisfactory in the line of increasing of work liability, stabile work of rising of level of energy transmission and distribution systems and purposeful measures are operated in the line of them.

Different setting repair work were operated at  energy blocks in accordance to measures plan in order to spend autumn – winter season of 2012/2013 in normal regime as at other  energy enterprises. At the same time, prophylactic repair work were operated at other electric equipments – noted enterprise was also added  information about carried out measures during last three months.

Lets` noted under stressing information given by the source, repair work was operated at energy block number 4. capital repair work of energy block number 6 is begun and measures are continued  under graphic. Different setting measures were implemented at other energy blocks.

Lets` also noted that, different setting measures were implemented at black oil vats, oil circuit breakers and TL. At the same time Different setting repair work were carried out at chemical workshops.

Inspection work is systematically operated there, indispositions observed as a result of technological process are eliminated. In additional, oil circuit breakers of the II Salyan TL by 110 kV are repaired.

Lets` noted at the end that, intended repair – restoration work are continued under intended plan. Collective are assiduously try to supply without interval and stabile work regime of energy blocks.

By  the way, fire safety is also in the center of the attention. The territory of workshops, administrative and subsidiary buildings were cleaned of dry grass and mass.

Lets` remind that, “Shirvan thermal power plant” consisting of 7 blocks each power by 150 MW is the first energy object in Europe. At present, construction of new power plant by 780MW  -  “Janub power plant” is systematically continued at Shirvan  in order to supply energy safety. Modern technologies making opportunity for using of gas, black oil and diesel fuel will be applied there. New power plant will be play important role in strengthening of energy safety of Absheron peninsula and southern regions, supplying of regular and stabile work regime of energy transmission and distribution systems.