CURRENT REPAIR MEASURES ARE IMPLEMENTED AT TL

Image

According to the information given by Electric Energy Transmission Office of  "Azerenergy" JSC to the Press – release of the Joint Stock Company, "Ganja REN" 110/35/6 kV belonging to the hotel, "Ganja-1", a large amount of work performed. Third 110 kV "Ganja" circuit breakers air  line, the current transformers have been repaired and the line separator. 31.5 MVA system number 2 engine cooling fans have been replaced by new ones. A strong number 3 in 6 kV transformer was repaired in the current transformer.

At the same time 110/35/10 kV "Zayam" 10 kV substation "greenhouse" and "Technology" TL vacuum circuit breakers, "Alabashli" 25 MVA transformer station number 1 record of 10 kV vacuum circuit breakers were repaired service. 500/330/110 kV "Samukh" s/s 630 kVA line also includes interchange repairs. As of the 1st and 2nd "Aluminiumzavod" 4 "Mingachevir" 3 "Shamkir", 2 and 3 "Samukh" maintenance repair work was carried out in different types of lines.

330/110/10 kV "Ganja" substation "Samukh", "Ganja", "Kura", "Central", "Shamkir" TL repair current circuit breakers and current transformers connected to the system.

The balance of "Ganja" REN company also changed Air Lines insulators expired. 4th 330 kV of "Mingachevir" TL 16 Q2 110 "Shamkir" TL 40, 1st 110 kV "Agstafa" TL 21 and 110 kV in the 2nd "Agstafa" TL is one of 24 pieces of work, progress on updating the insulator. "Ganja REN" 110/35/6 kV belonging to the hotel, "Ganja-1", a large amount of work performed. Third 110 kV "Ganja" circuit breakers air line, the current transformers have been repaired and the line separator. 31.5 MVA system number 2 engine cooling fans have been replaced by new ones. A strong number 3 in 6 kV transformer was repaired in the current transformer.

At the same time 110/35/10 kV "Zayam" 10 kV substation "greenhouse" and "Technology" TL vacuum circuit breakers, "Alabashli" 25 MVA transformer station number 1 record of 10 kV vacuum circuit breakers were repaired service. 500/330/110 kV "Samukh" s/s 630 kVA line also includes interchange repairs. As of the 1st and 2nd "Aluminiumzavod" 4 "Mingachevir" 3 "Shamkir", 2 and 3 "Samukh" maintenance repair work was carried out in different types of lines.

330/110/10 kV "Ganja" substation "Samukh", "Ganja", "Kura", "Central", "Shamkir" TL təmirlərdən current circuit breakers and current transformers connected to the system.

The balance of "Ganja" REN company also changed Air Lines insulators expired. 4th 330 kV of "Mingachevir" TL 16 Q2 110 "Shamkir" TL 40, 1st 110 kV "Agstafa" TL 21 and 110 kV in the 2nd "Agstafa" TL is one of 24 pieces of work, progress on updating the insulator.