REPAIR MEASURES ARE IMPLEMENTED
During the month of July, "Ganja REN", belonging to the balance of power transmission lines, substations companies, maintenance and repair work carried out. In the western region of the country plays an important role in energy supply repairs maximum advantage of favorable weather conditions. S/s plant and equipment, high-voltage lines made in accordance with the approved plan of activities.
Number of REN "Azerenergy" JSC, in accordance with the information 110/35/6 kV "Ganja-1" Maintenance work is carried out s - № 1 to 20 MW and 31.5 MW, 2 and 3 do not have transformers, circuit breakers and current transformers 110 kV , 110 kW, as well as the 1st, 2nd, "Dashkesan", 5th, 6th, 7th and "Ganja", 1st, 2nd "Melxior" TL switches (EA) and current transformer (CT) of this kind. s/s 6 kV transformer oil remains in the spotlight switches and vacuum switches. 2 110 kV "bus" transformers, 35 kV of 1st, 2nd and 3rd, and "bus system" gaps in the current-voltage transformers have been repaired.
110/35/10 kV Mechanical Brigade "Ganja-2" substation continue to work. 10 kV "Motel" TL current circuit breakers vacuum circuit breakers were repaired. High "zəyəm, shamkir" substation 10 kV "artesian-Deller" TL oil circuit breakers were replaced by vacuum circuit breakers. In addition, 10 kV "greenhouse" and "technology" TL current circuit breakers vacuum circuit breakers were repaired.
And 500/330/110 kV during the current repairs "Samukh" 330 kV substation in the 1 st, 2 nd, "Aluminium zavod", 3 "Shamkir", 2 nd, 3 rd "Samukh" equipments overhead line 330 kV circuit breakers tires 2nd him "Tyre System" is the separator and current transformers there. 110 kV similar processes, such as the 2nd, 5th, 6th and 7th "Ganja", 1 "Center", 2nd "Yenikend" was held in the OHL.
Agstafa 330/110/10 kV, 110 kV substation feeding "Poylu" TL current circuit breakers and current transformers were repaired. Both began to overhaul 125 MVA.
The process was carried out to replace the insulators. The third 330 kV "Shamkir" TL 80, 110 kV "Yenikənd" TL 40 "Agstafa" TL 70, as well as other lines of more than 30 to 35 kg wire insulators changed.
"Ganja" REN objects repairs have been successfully implemented in August.