THE CURRENT REPAIR MEASURES ARE IMPLEMENTED
"Azerenergy" JSC electrical corporation's press service, which said last month that "Mingachevir REN" substations belonging to the continued maintenance and repair companies.
220/110/10 kV "Aghsu" 10 kV transformer substation No. oil circulation 2 post has been renovated, 63 MVA of current repairs. According to information received, Mingachevir 110/35/6 kV "Sheher" substations of 35 kV oil circuit breakers were repaired. In addition, current repairs were carried out. The "City" 4 substation 6 kV switch the input of fat, 15 of the "Bonds» TL vacuum circuit breakers, air-line number 39 in the current oil circuit VMPE-10 type have been repaired.
Repairs Gabala, Naftalan, Yevlakh, Ujar and Agjabedi regions performed in substations. 220/100/10 kV "Gabala" substation was put into operation and maintenance of the three key elements of fat. 110/35/10 kV "Naftalan" and "Basic" Five oil circuit breakers at substations in the capital, including three oil circuit breakers, vacuum circuit breakers connected to the service network.
Prefer 110/35/10 kV "Ucar" and "Agjabedi" in July substations repairs. 1st 110 kV "Kurdamir" and 3 "Ucar" circuit breakers 110 kV overhead lines, 35 kV the 2 "Aghjabedi" Air Line Oil were reconstructed.
110/35/10 kV "Great HARAMI" 16 MVA transformer station number 2 in the current repairs of 110 kV "Fizuli-1", "Khalaj", "Fuzuli-2", "Qozluchay", "Barda", "Shukurbeyli "lines, circuit breakers and oil circuit number 2 was a 16 MVA transformer. During the reporting period was dominated by the current repairs.
The proposed action plan and overhaul of the current "Mingachevir REN" other objects continued LLC.