THE MEASURES ARE OPERATED IN ACCORDANCE TO PLAN
"Ganja High Voltage Electrical Networks", belonging to the balance of the line of work and improve the quality of equipment and technology to meet the needs of the enterprise team of mechanics are trying to take advantage of favorable weather conditions. They are 330, 110, 35 kV and at the same transmission lines to carry out inspection and testing, as well as the overhaul of the plan provided by the current and the proposed measures are implemented.
Despite the hot weather, the 330 kV "Gardabani" IV "Agstafa", IV "Mingachevir" I "Goranboy", as well as 110 kV I "Agstafa", IV "Ganja", the second "Shamkir", I- II "Yenikend" I -II "Dashkasan" I "Shamkir" TL insulators have been changed where necessary cables were replaced with new ones. Repair of the campaign from the beginning of insulators were changed during the six months of 1000.
110 kV II "Agstafa" TL more than 360, 110 kV "Shamkir" TL have changed in more than 190 insulators were replaced. Other high-voltage insulators different number of lines changed, painted pillars. 110 kW I "Shamkir" TL 25 kilograms of the required cable has been extended.
330/110/10 kV within six months of the year, "Agstafa" and 110/35/10 kV "Ganja-2" carried out reconstruction work in substations. Maintenance and repair work has been done in other substations. 110/35/6 kV "Ganja-1" to 20 MVA substation number 1, 2 and 3 operating MVA 31.5 repaired. As of 35 kV I-II "birder", I-II "," Goy line, 6 kV I "military units", "Fatoglu" I-II "Emergencies", I-II, "Sheher" second "Instrument" and other air lines service.
"Ganja" on HVEN 110/35/6 kV "Ganja-2» № 1 and 2 transformer substations of 25 MVA, 35 kV and current inputs oil circuit breakers were repaired. In addition, 10 kV , "Balchili", "overhead power lines were restored. This process, "Osman", "Asfaltzavod", "Engineering", "airport", "Nadel" continued vacuum circuit breakers and other power lines have been repaired.
It should be noted that the mechanical brigade 330 kV "Ganja" and "Ganja Automobile Plant" 500 kV substation and "Samukh" 110/35/6 kV "Zagam" and "Alabashli" substations, as well as 330 / 110/10 kV "Agstafa" substation repairs were carried out on the basis of current and design.
"Ganja" HVEN scheduled for the second half of the current and capital repair work continues.