MINGACHEVIR REN: REPAIR MEASURES ARE IMPLEMENTED
"Azerenergy" JSC Electric Power Transmission Office press service of the Joint Stock Company said that other energy facilities "Mingachevir Regional Electric Network" (REN) is carried out and appropriate measures to prepare for the season. In particular, the planned measures are mainly carried out and a number of fire safety measures have been implemented.
So in the last four months of the year, "Mingachevir" REN 110/35/6 kV belonging to the "City" 40.5 MVA power transformer substation No. 1 renovated its 35 kV oil circuit entry were replaced with new ones; 40 kVA use transformer connected to the 0.4 kV; The new SCC-10-type socket mounted on the first section; The new 6 kV cable line sections I and III of the distribution transformer No. 1 out of 6 kV oil circuit breaker tire entry portal designed to connect the bridge; 1st and 2nd shaky air line (TL) circuit breakers were repaired.
At the same time, during this period, 110/35/10 kV "Main" and the work done in transformer substation No. 1 and 2, No. 2, 110 kV and 10 kV transformer oil is the key to entry renovated; JBI-16 to 35 kV, 10 kV, 3rd Agriculture, Pump, Fuel Depot, Poultry and several other TL oil circuit breakers were repaired and put into normal working condition.
220/110/10 kV during this period, "Aksu", "Gabala", 110/35/10 kV "Ucar", the voltage "Barda", "Khalaj", "Aghjabadi", "Naftalan" and At a number of other different types of repair work carried out.
In general, in the last four months of the year, "Mingachevir" REN substations belonging to 11 different voltage transformers, 220 kV, 13 units, 110 kV and 35 kV 35 7 6-10 14 kV oil circuit breakers were repaired and put into normal operation. At the same time during this period in order to regulate the level of 5.5 tons of transformer oil transformer oils were developed.
Electric Power Transmission Office also reported that the country's energy system is extremely strategic for the 1st and 2nd "Absheron", 1st, 2nd and 6th "Mingechevir" power transmission line (TL) in the spotlight.
It should be noted that during this period "Mingachevir" REN service territory of Ganja 110 kV in the 1st, 3rd Main, 1st and 2nd Ucar, 2nd, 3rd and 4th Barda 220 kV 1st Mungəcevir, 330 kV 1st Absheron, Mingachevir 4, 500-kV transmission lines at the 2nd Absheron different types of repair work carried out. This includes the replacement of insulators and conductors, (sleyflərin) and stands outline repair, cleaning and other work dates back to the line trace of green grass.
Stipulated in the action plan is carried out on a regular basis, and it is stable and continuous power, as the country is an important factor in securing a job.
"Mingachevir" REN, Mingachevir, Agdash, Agsu, Goranboy, Barda, Yevlakh, Ujar, Agjabadi, Beylagan, Naftalan and Fizuli regions of the energy transfer of energy to carry out the operation.