FOR MUCH MORE INCREASING OF EXPLOITATION LEVEL

Image

Important measures were taken in the line of enlarging of distribution electric network, increasing of quality of electric energy. Reconstruction and repair work were implemented at Goygol” EN belonging to Ganja REN as at other energy objects.

According to the information given by mentioned enterprise to the Press – release of “Azerenergy” JSC, some measures were implemented in the line of preparation to autumn winter season and increasing of exploitation level during 10 months of the current year.

Thus, to create a system of accounting meter, most importantly, increase the level of user charges in order to improve serving  were established in 1000 smart card log , 6 km of 18 kV cable line . 6 and 10 kV at the same time more than 7 km repairs performed for any purpose, including 700 m line was restored. 0.4 kV network part about 13 km from the capital and current repairs are carried out. Incidentally, at this time, the joint distribution device and three TM has been installed, as well.

Note that the network of petrol stations in nearly 100 different types of work carried out repairs of transformers . In addition, 10 different power transformers have been repaired and re- connected to the network.

The report also says that as a result of the technical and economic indicators of the positive trend was observed . So, in October of the current year compared to the total consumption of the same period last year increased by 1.1 million kWh of more than 7.6 million . By the way , the constant people consumer group 2,6 million kWh electric power was used , compared to the same period of the previous year more than 345 thousand kWh . Payment during the reporting period in comparison with the same period last year increased by more than 17 per cent . It should be noted that during the 10 months of the current year, a total of 73.4 million kWh electric power was used . Istehklak compared to the same period last year increased by 5.1 million kWh , the payment was more than 10 per cent of the absolute increase . By the way , the constant people consumer group more than 21 million according to these figures , there were about 563 thousand kWh and 8 . Under other information given by the source , during the raids on the territory of the current year , in October, consumers accounting for 69 violations were discovered complete . Discovered violations of rule were acted , 18.4 thousand to 306.9 thousand kWh loss electric power was restored use value.

By the way , during the 10 months of the current year , according to the infringements in question in the territory of the enterprise has been drawn up by nearly 380 , 2 million 863.5 thousand kWh loss electric power was restored 171,8 thousand manat use value . Actions carried out in 76 per cent of this sum was repaid and the corresponding measures are carried out in accordance with the payment of the remaining sum .

It should be noted that the discovery rule applies to violations of the enterprise in oktyar a consumer ( within 10 months and 8 consumers ) to take the documents to the law - enforcement authorities .