KHACHMAZ REN: THE POWER OF S/S ARE INCREASING
“Khachmaz Regional Electric Network” (REN) plays the main role in electric energy supply of northern region of the republic.
According to the information given by REN to the Press – release of “Azerenergy” JSC, urgent measures were implemented and presently continued for increasing of exploitation level at all networks of above mentioned objects. So that, transformer number 2 by 25 MVA was substituted with the one by 40 MVA in accordance to power increase at “Guba” s/s by 110 kV. At the same time, insulating circuit 110 kV transformer at the same time, the line disconnector, access to the oil circuit breakers, as well as number 1 and its 35 transformer 40 MVA, 10 kV equipment, such as the use of 110 kV transformers I-II "Guba" HEVX disconnector line was restored.
Incidentally, the above-mentioned period, 35 kV "Findighan" 1,8 MVA of transformer substations with a capacity for 2,5 MVA replaced. At the same time, 330 kV "Xachmaz" substation capacity of 180 MVA, two conducted a test measuring the voltage converter transformer tested under load, current transformers and 110 kV voltage measurements and tests were conducted. In addition to all these, 110 kV "Hussar" S of repair work was carried out setting, and a new 10 kV distribution structure, the construction work was going on behind closed doors.
Note that the 110 kV "Shabran", "Siyezen", "Broiler", 35 kV, "Guba", "Channel", "Nabran", "Canal", "Zeykhur HPP", "Zeyve" repair substations conducted to further strengthen its sustainability.
The source also said that during the reconstruction and repair work on the part belonging HEVX. Thus, the new 110 kV II "Laza" HEVX put into operation. At the same time, 330 kV "Xachmaz", "Derbend" 110 kV "Xachmaz", "Khudat-Yalama" and the other was held in a number of different types of lines. In general, a period of 35 kV and above about 96 km HEVX repair and restoration work carried out.
It should be noted that the net balance of the section 110 and 35 kV for the implementation of a number of planned projects. Thus, as is well known, this region of hot summer days, there is a strong influx turistov.Neobhodimost create large-scale power plants in the region, the report said. Gechresh to adequate food and Tangi-six new substations of 35 kV in the village of completion of the 110 kV "Nabran" substation construction work is planned.
Finally, it should be noted that, according to the company health and safety rules are respected in the grave. Different climate and landscape of the area of service for staff is cətinlilkər. Taking this into account, before undertaking any transaction trained technical staff and workers are provided with the necessary protection.